252 MW Gas Turbine Power Plant

PROJECT

Fast track Project: Bouchemma Gas Turbine Power Plant 252 MW (2 GT GE frame 9E x 126 Mw)

Client

GE

Location

Tunisia

SCHEDULE

  • 11-2015/06-2016
  • 10-2016 / 04-2017

SCOPE OF WORK

Phase 1:

  • Civil engineering and works (including earth moving, miscellaneous roads and network, Concrete Stations, Turbine House)
  • Site assembly, testing and industrial commissioning of electro-mechanical equipment, as well as auxiliary and ancillary works
  • Steel Structure works
  • Piping works
  • Electrical works