ASHTART Offshore Platform

PROJECT 

ASHTART Offshore Platform: Fabrication Load out sea fastening and Hook-up of 2000 Tones

Client

ELF / SEREPT

Location

Tunisia

SCHEDULE

1994-1995

SCOPE OF WORK

EPC project :Construction of bridge ASPF3:


Detailed Engineering, Procurement, Construction, Precommissioning, sea fastening, load out, hook up, Commissioning and Start up including:

  • Fabrication and erection of steel structure,
  • Piping design, procurement, fabrication and installation,
  • Process equipment fabrication,
  • Equipment installation,
  • Electrical and control room installation,
  • Electrical and instrumentation works,
  • Transport and Loading of bridges on cargo-Barge.

Structure: 1200 tons

Piping: 200 tonsEquipment: 400 tons

Others: 200 tons