PROJECT

Expansion of the Transtunisian Export Gas Pipeline : Gas Compressor Stations
Client
Snamprogetti / Nuovo PignoneLocation
TunisiaSCHEDULE
2007-2009
SCOPE OF WORK
Sbeitla new Gas compressor station:
- civil engineering works
- turnkey construction of 7 buildings
- prefabrication and installation of 4400 tons of pipe
- installation of mechanical equipment supplied by the Client
- electro-instrumental installation and telecommunications
- assistance to commissionning
Adaptation of Feriana Gas compression station :
- prefabrication and installation of a batch of 450 tons of pipes
- insertions operations on existing collectors
- installation of mechanical equipment
- civil works
- electro-instrumental installation and telecommunications
Korba Gas compressor station:
Installation of 3 GasTurbo Compressors (civil works, structural erection, piping erection, instrumentation, equipement installation, commissioning and start-up)
Haouria Gas compressor station:
Ravamping, overhauling of old turbo-compressors (seven skids) and installation of new units