Fire Protection & Cooling System
PROJECT
EPC Contract for Fire Protection & Cooling System of LNG tanks at GL1Z complex
Client
Sonatrach
Location
Algeria
SCHEDULE
2008-2011
SCOPE OF WORK
Pumping System "8 Unit Motor Pumps 2685m3 / h, Network of 2km of 38", water storage tank 35000m3, Detection and Control System, Electrical Room:
- Basic and Detailed engineering of the new system
- Supply and installation of a new water storage tank (35000m3)
- Complete design of eight main pumps and two Jockey pumps
- Study, Supply and Installation of the inlet piping of pump,
- Installation and commissioning of the sprinkler system
- Providing spare parts for installation and commissioning
- Sonatrach personnel Training.