252 MW Gas Turbine Power Plant
PROJECT

Fast track Project: Bouchemma Gas Turbine Power Plant 252 MW (2 GT GE frame 9E x 126 Mw)
Client
GE
Location
Tunisia
SCHEDULE
- 11-2015/06-2016
- 10-2016 / 04-2017
SCOPE OF WORK
Phase 1:
- Civil engineering and works (including earth moving, miscellaneous roads and network, Concrete Stations, Turbine House)
- Site assembly, testing and industrial commissioning of electro-mechanical equipment, as well as auxiliary and ancillary works
- Steel Structure works
- Piping works
- Electrical works