120 MW Gas Turbine Power Plant

PROJECT

BOUCHEMMA Gas Turbine Power Plant 120 MW (1 x 120 Mw Gas Turbine Type GE Frame 9E)

Client

NUOVO PIGNONE

Location

Tunisia

SCHEDULE

1998 - 1999

SCOPE OF WORK

  • Civil works ( Earth Works, foundations, buildings, roads, turbine house, etc.. )
  • Steel Structure detailed design, fabrication and erection.
  • Turbines and Equipment Installation
  • Storage tanks design, fabrication and erection
  • Piping detailed design, fabrication and erection
  • Electrical and Instrumentation works.
  • Transformer station
  • Auxiliary station
  • Technical Assistance to commissioning and Start-up